Managing rising construction costs without compromising on quality

Managing rising construction costs without compromising on quality

27 November 2026 Consultancy-me.com
Managing rising construction costs without compromising on quality

With construction costs rising across the UAE, property owners, developers and businesses are facing growing challenges in keeping their projects on budget. David Rees, CEO of LXA, outlines how effective cost planning, proactive risk management and independent advice can help clients achieve cost certainty without compromising on long-term value.

For property owners and businesses planning their next project, it’s natural to ask how much confidence they can really have in their budget right now. Cost certainty is still achievable, but you need to know which figures you can rely on and where to leave flexibility.

Costs were already under pressure from strong demand, labour shortages and longer lead times even before the regional conflict. And those pressures have since increased due to rising shipping and insurance costs, higher fuel prices and supply chain disruption.

According to figures from Turner & Townsend and AECOM, construction costs in the UAE are forecast to rise by 5–8% in 2026, with luxury residential and fit-out projects particularly exposed. Among our high-end projects we have seen prices for some imported high-end materials up by 20–25%.

However, it’s not only about inflation or external market conditions. Some of the biggest cost overruns happen when projects start before the design is ready, when clients make changes during construction, or when important decisions are made too late. Another common mistake is going directly to a contractor without having prior independent project and cost management advice.

The wider impact

The challenges play out differently across sectors. High-end residential and hospitality projects often rely on imported materials and specialist suppliers, and bespoke detailing makes lost time difficult to recover. On a luxury residential project, even small design changes during construction can put the timeline at risk. Trying to accelerate things by overlapping trades or rushing installations can compromise standards, add costs and cause further delays.

Commercial and retail projects are particularly sensitive when opening dates are fixed. We sometimes see fit-outs start before the design is fully developed in an effort to meet those dates. Contractors have to price the work on incomplete information, and costs become harder to control as variations mount. For investors and developers, the impact goes beyond higher construction and financing costs. A late opening delays revenue, constrains cash flow and can reduce the expected return on investment.

Knowing what to count on

Cost certainty is still achievable, but it depends on how far the design has progressed and how clearly the scope and risks are defined. An early budget is an informed estimate. It becomes more reliable as specifications are agreed and major packages are tendered. Even after the contract is awarded, variations and unforeseen conditions can affect costs. The key is being clear about what’s fixed, what’s estimated and where risks remain.

Cost planning should begin alongside the design brief and cover the full cost of delivering the project. That includes construction, professional fees, approvals, taxes and contingency, as well as costs outside the main contractor’s scope, such as furniture, specialist equipment and utility connections. Establishing the total budget early helps us work with the design team to understand what it can realistically deliver in terms of size, quality, specification and programme. It’s much easier and less expensive to adjust the design on paper than to cut scope or compromise on quality once construction is under way.

A realistic contingency is crucial, and the amount should reflect the project’s risks, accounting for how far the design has progressed, how the work will be procured and the level of complexity. On longer projects, it’s particularly important to consider how inflation, material price rises and delays could affect costs. As the design develops and more costs are confirmed, you can review and adjust the contingency. Its purpose is to cover risk; budget design changes or upgrades separately.

Ordering early can make a real difference, particularly for items with long lead times, such as mechanical and electrical equipment, bespoke joinery and imported finishes. But ordering before the design and specifications are clear can be as risky as leaving it too late. Where it makes sense, we agree prices, reserve manufacturing capacity and identify alternative suppliers well before a delay could hold up the project. We also consider the supplier’s capacity, financial stability and track record for quality and delivery, as a lower price is worth little if the supplier can’t deliver what you need on time

Protecting value when costs rise

When costs rise, the first step is to understand what’s driving the increase. Some increases may be justified, but we shouldn’t accept a blanket percentage. We should also consider whether there is a more efficient way to achieve the same result. Always be cautious about any saving that compromises quality, durability or how the building performs over time. On high-end residential and hospitality projects, finish quality is central to the property’s value.

A saving during construction can quickly become a false economy if it means higher maintenance costs or replacing something sooner than expected.

Keeping costs under control

Based on our experience at LXA, we see four clear opportunities for keeping costs under control:

  • Start with a realistic budget and a clear scope and develop the cost plan alongside the brief.
  • Compare tenders on the same basis and understand any exclusions or risks before awarding the contract.
  • Keep the forecast up to date. Once work begins, track progress, check payments and assess the cost of changes before approving them.
  • Independent advice protects the client’s interests by having someone to challenge costs and explain the implications of a decision.