Liquidated damages in construction under the UAE’s new Article 340

Liquidated damages in construction under the UAE’s new Article 340

19 August 2026 Consultancy-me.com
Liquidated damages in construction under the UAE’s new Article 340

Article 340 establishes the UAE’s new framework for pre-agreed compensation, including liquidated damages for construction delays, and defines when courts can reduce or increase the agreed amount. Experts from CSQ outline what Article 340 means for the Commercial Manager of construction projects.

Most liquidated damages claims in the UAE start life as a simple sum. Days late, multiplied by the daily rate written into the contract, equals the amount owed. It is a clean equation, but it has also always been slightly fictional.

On 1 June 2026 the UAE’s new Civil Code came into force, replacing the Civil Transactions Law of 1985 in its entirety. For the construction industry, the change that matters most sits in Article 340, which governs compensation the parties agree in advance.

In the world of construction and capital projects, that means the liquidated damages clause, the daily or weekly figure fixed for late completion. It replaces Article 390, it is mandatory, and it applies to contracts entered into from 1 June 2026. Earlier contracts stay under the 1985 law.

What Article 340 says

Read “debtor” as the contractor paying delay damages and “creditor” as the employer claiming them.

  • The contracting parties may pre-determine the amount of compensation by stipulating it in the contract or in a subsequent agreement, subject to the provisions of the law.
  • The court may reduce the amount of agreed compensation if the debtor proves that the assessment was excessive or that the original obligation has been partially performed.
  • The court may reduce the amount of the agreed compensation if the creditor contributed by their own fault to the occurrence of or increase in the damage, or may refrain from awarding compensation if the creditor’s fault predominates over the debtor’s fault.
  • The creditor may claim an amount exceeding the agreed compensation if they prove that the debtor has committed fraud or gross fault.
  • Any agreement contrary to the provisions of this Article shall be void. Article 340, Federal Decree-Law No. 25 of 2025.

What actually changed

Article 390 gave the court a broad discretion to adjust the agreed sum, up or down, so that it matched the actual loss. Article 340 replaces that general power with a defined list, and tells you who has to prove what.

There are three ways the number can come down: an excessive assessment, partial performance, and employer contribution to the delay. There is one way it can go up, and it is gated behind fraud or gross fault.

That gate is narrower than the one it replaced. Under Article 390 an employer could ask the court to raise the agreed sum on proof that its actual loss was greater. Article 340 does not carry that ground forward. An increase now requires fraud or gross fault.

Some commentary reads sub-article 4 the other way, as arming employers, on the basis that the rate no longer caps exposure where misconduct is proven. That holds against market habit, which treated the rate as maximum exposure. It does not hold against the statute it replaced, which already permitted an increase on ordinary proof of loss.

Set against that, Article 340 replaces a general judicial discretion with a defined list of grounds and a stated burden of proof. Read one way that is a gain in certainty, and much of the commentary reads it exactly that way. The distinction worth drawing is what kind. You now know what a court can do to your number, on what grounds, and who has to prove it. You do not know the number any better than you did.

The rate remains reducible on three separate grounds and can no longer be topped up when the loss turns out worse than the estimate. Article 340 gives you certainty about the process. It does not give you certainty about the recovery.

What this means for projects

Article 340 does not adjust your number automatically. Sub-article 2 reduces the rate only where the contractor proves the case for it. Sub-article 4 increases it only where the employer proves fraud or gross fault. Every route has to be proven, using delay records, cost substantiation, or expert evidence.

The rate is a claim, not a number. A court may reduce a rate it finds excessive, so the figure needs to be proportionate to the loss you can realistically anticipate, and you need to be able to show the working. UAE law does not test whether the rate was a reasonable estimate at the date of signing. It tests whether the sum is excessive against the loss actually in issue, at the point the claim is made.

Documenting the basis of the rate is self-protection rather than a statutory requirement, and it belongs at tender stage, not at the point of dispute. A round number carried over from the last project invites a challenge.

Keep contemporaneous delay records. Whether you are enforcing a claim or resisting one, the result turns on the evidence you can produce, not on how the clause is worded. Contemporaneous records, notice compliance, extension of time administration, and a delay analysis that stands up. The grounds for cutting your claim are now written down and easier to aim at. So are the grounds for defending it.

Where the employer contributes to delay. Where the employer has contributed to the delay by its own fault, the contractor has a clearer basis than before to argue for a reduction, and on the right facts for no compensation at all. Whether a tribunal goes there will turn on causation and expert delay evidence. The party with the clean, real-time delay record is in the stronger position. The party relying on a story assembled after the fact is exposed.

Termination remains unresolved. Article 340 is silent on what happens to liquidated damages when a contract is terminated. That gap sits alongside how the clause is drafted, whether the sums had accrued before termination, and whether general damages are available instead. An employer who assumes it can terminate for default and still bank its delay damages should test that assumption against the contract before acting on it.

The key takeaway

The practical point is this: your liquidated damages number is only as strong as the record that supports it. Article 340 rewards the discipline good commercial management has always demanded. Price delay risk on evidence, record it as you go, and treat the liquidated damages clause as the start of the argument rather than the end of it. The contracts most exposed are the ones where the number was agreed and then forgotten.